EUROGRUAS extracts the ferrules of the coke chamber at Repsol’s refinery, in Puertollano

EUROGRUAS extracts the ferrules of the coke chamber at Repsol’s refinery, in Puertollano

March 2012

Last 1 March, Repsol started the multiannual maintenance stop in the plant of Puertollano (Ciudad Real), which is aimed at checking the equipment, conducting maintenance works and executing several technical improvements. The stop will last around 50 days and will be funded with an investment of 28 million Euros.

Grúas y Transportes Gil becomes EUROGRUAS OCCIDENTAL

Grúas y Transportes Gil becomes EUROGRUAS OCCIDENTAL

March 2012

Grúas y Transportes Gil, S.A. becomes a limited liability company and changes its name for EUROGRUAS OCCIDENTAL, S.L.U., as part of the globalisation process the trademark is embarked on, and as EUROGRUAS VALERIANO (Grúas Valeriano) had done before and, this year, EUROGRUAS ORIENTAL (Grúas Alhambra).

Bridge crawling and sliding to expand the railway of the high speed train (AVE) between Seville and Almeria

Bridge crawling and sliding to expand the railway of the high speed train (AVE) between Seville and Almeria

January 2012

EUROGRUAS, through its Heavy Lift Division, has taken part in the expansion of the AVE’s railway between Seville and Almeria, crawling and sliding the central span of a metallic bridge 97.2 m long, 13.2 m large, 19.5 m high and 650 t.

Grúas Alhambra changes its name for EUROGRUAS ORIENTAL

Grúas Alhambra changes its name for EUROGRUAS ORIENTAL

December 2011

EUROGRUAS’ Board of Directors has approved the change of name for Grúas Alhambra, S.L.U. From 1 January, it will be called EUROGRUAS ORIENTAL, S.L.U.

The branch will keep on offering cranes, special transports and tower cranes for rental at its offices, all over the province of Granada (Loja, Guadix, Baza and Peligros) and Malaga.

Transport of 4,500-ton Jacket for the Castor project

Transport of 4,500-ton Jacket for the Castor project

November 2011

At the end of 2007, Escal UGS assigned the Castor project to UTE Casgas Off-Shore, regarding the construction of a warehousing plant of Gas Natural, taking advantage of the geological morphology existing under the Mediterranean Sea, located at more than 1,750 metres deep and 21 km from the Vinaròs coast (Castellón). Gas Natural’s underwater warehouse was mainly aimed at improving the efficiency and security of the Spanish gas system.

EUROGRUAS sets up again the structure for the Tennis Davis Cup in Seville

EUROGRUAS sets up again the structure for the Tennis Davis Cup in Seville

Noviembre 2011

As it had already done in 2004, Lanik has assigned to EUROGRUAS the assembly of the provisional structure that will hold the final of the Davis Cup between Spain and Argentina next 3, 4 and 5 of December, in La Cartuja Stadium

EUROGRUAS in charge of assembling the main pieces of equipment for the new C.T.C.C. plant in Lithuania

EUROGRUAS in charge of assembling the main pieces of equipment for the new C.T.C.C. plant in Lithuania

March 2011

Iberdrola Ingeniería y Construcción assigned to itself the construction of a combined cycle plant in the town of Elektranai (Lithuania), with the capacity to generate 440 MW and a planned investment of 330M EUR.

The works started in September 2009 and were supposed to last 3 years, assigning to EUROGRUAS the unloading, internal transport and placement of the main equipment over the bedplates, which weighed up to 342 tons.

About Eurogruas

EUROGRUAS is a company specialized in providing engineering, assembly, lifting and special transport services through self-propelled cranes and alternative systems with our own means and skilled operators. Our company gathers the necessary organizational structure and capacity of management to provide global solutions.