April 2015
EUROGRUAS has completed the first phase of the work committed by Repsol within the project T-72 with the stockpile of the second reactor, moved from the Castilla South Pier to Tarragona Refinery.
For the realization of these works, consisting of special transport and stockpiling in refinery, until their subsequent assembly at the end of the year when will be the replacement of the existing reactors of the ISOMAX unit, EUROGRUAS has been used 16 axles of modular trailer GOLDHOFER driven by 2 tractor truck IVECO joined by double drawbar.
Both maneuvers of transport of the reactors (320 tons of weight and 3,80 m. of diameter each one) took place in consecutive days and were carried out at night due to the complexity of the same, being momentarily cut the T-750 road.