News

Transport and setting up of the new 50-MW plant of energy generation from biomass in Ence (Huelva)

Transport and setting up of the new 50-MW plant of energy generation from biomass in Ence (Huelva)

May 2012

EUROGRUAS transports the gas turbine, the last big piece of equipment belonging to the project of the factory located in Ence, starting thus the last stage of the construction of the largest biomass plant in Spain, with a power output of 50 MW.

The A gas turbine is composed of a generator (107 t), a turbine (184 t) and a condenser (114 t) and has required a special convoy with 16 goldhofer lines equipped with shaft and 2 tractors in order to be moved from the port of Huelva to the facilities of Ence, in San Juan del Puerto.

EUROGRUAS HEAVY LIFT will undertake the setting up of these pieces of equipment, as it has already done with the boiler, using modular gantry frames and sliding systems.

About Eurogruas

EUROGRUAS is a company specialized in providing engineering, assembly, lifting and special transport services through self-propelled cranes and alternative systems with our own means and skilled operators. Our company gathers the necessary organizational structure and capacity of management to provide global solutions.